The Go On
Wet Heating Corporation
· It is suitable for new construction
· There is no risk of freezing in winter because hot water pipes are not used
· After construction, cement is completed, so the floor is hard
·The cement is heated to keep warm for a long time
Order of construction
1. Install insulation (4.5mm)
2. Arrange carbon fiber heating elements
3. Attach the aluminum heat diffusion sheet
4. install a glass fiber mesh
5. thermostat installation
6. Fever test
7. cement-pouring construction